BIRD 2026–2035
Chapter 7
Policy Recommendations and the Way Forward
Institutional enablement, territorial delivery, investment mobilisation, and governance learning for continuity beyond 2035
Bangsamoro Investment Roadmap Development (BIRD) 2026–2035

Bureau of Investments, Ministry of Trade, Investments and Tourism (BOI-MTIT), BARMM
October 2026
Chapter 7

Contents of this Chapter

How to read this chapter. Each recommendation carries an identifier (A1–D5), an accountable owner, a time horizon, the Critical Leverage Point (LP1–LP5) it serves and the BEIE cluster it acts on. The consolidated matrix in Section 7.2 lists all twenty-one recommendations on one page for cabinet and parliamentary use.
BIRD 2026–2035 · Chapter 7Page 2
Chapter 7
Chapter 7

Policy Recommendations and the Way Forward

Chapter summary

Chapters 1–6 establish the evidence base, BEIE diagnosis, Integrated Ecosystem Development Strategy (IEDS), performance measures, causal pathways, and phased implementation architecture. Chapter 7 converts those findings into a coordinated policy and institutional agenda. It addresses the conditions needed to sustain delivery through political transitions, fiscal constraints, climate shocks and security disruptions.

The central policy proposition is that investment opportunities and incentives will not by themselves produce transformation. The binding constraint identified in the preceding chapters is institutional throughput: the ability to turn a credible opportunity into a prepared project, lawful decision, financed investment, operating enterprise and measurable public value. Recommendations therefore prioritise institutional clarity, investability, reliable data and accountable delivery—not an undifferentiated expansion of incentives.

7.5%Illustrative annual growth required to reach the ₱550B stretch target from the cited five-province 2025 base; verify price basis and series first
11.5%Modelled chained throughput after applying the governance factor; diagnostic, not an observed investment-conversion rate
3.33/5Enablers readiness, the lowest of six clusters, against the highest urgency (4.04/5)
0Validation respondents from Basilan and Tawi-Tawi, the two island provinces

Sources: growth path computed from PSA-reported 2025 growth and the ₱266.59B five-province GRDP cited in MTIT (2026a); readiness from the BIRD Validation Survey (n = 76 consented responses, 3–20 August 2026).

Why this chapter exists

A roadmap fails in one of three ways. It is ignored when governments change; it is executed in silos so that one cluster's success is cancelled by another's bottleneck; or it drifts, with targets quietly lowered to match performance. Chapter 2 named these patterns as the Fixes that Fail, Shifting the Burden and Drifting Goals archetypes (Senge, 1990), and Chapter 3 located the leverage points that counter them (Meadows, 1999). Stakeholders confirmed the risk: drifting goals scored a vulnerability index of 3.03 of 5, and political transition 2.85 of 5, in the Validation Survey. Chapter 7 therefore treats continuity as a design problem rather than an aspiration.

The chapter is organised around the four areas set out in the Executive Summary: (A) policy and institutional enablers; (B) planning, budgeting and territorial delivery; (C) investment mobilisation and market development; and (D) governance of the way forward.

Relationship among the four instruments. BIRD supplies strategic direction and results logic; the Investment Code should supply statutory authority and rules on registration/incentives; the BIF-Net EO and implementing rules should organise case coordination and inter-agency facilitation within existing legal mandates; and the Investors’ Guidebook should translate approved rules and verified procedures into an accessible investor journey. The Guidebook does not create rights or incentives, the EO cannot amend statutes or waive statutory requirements, and the Roadmap does not itself appropriate funds or approve projects. All four should use a common, version-controlled evidence and performance framework.
BIRD 2026–2035 · Chapter 7Page 3
Chapter 7

Six policy design rules

Table 7.1. Design rules applied to every recommendation
RuleWhat it means in practiceArchetype it guards against
1. Relax the binding constraint firstSpend effort where readiness is lowest relative to urgency; a stronger link elsewhere adds little while the weakest link holds.Limits to Growth
2. Rules before rewardsWhere legally authorised, tie incentives to clear eligibility, performance commitments, monitoring and proportionate remedies. Assess fiscal costs and additional public benefits, and provide due process for suspension or recovery.Fixes that Fail
3. Build capacity, not workaroundsFund institutions to do the work rather than routing around them through ad hoc task forces.Shifting the Burden
4. One baseline, one target pathMaintain one controlled register of definitions, geography, baseline year, data owner, source, target path and revisions. Separate verified statistics, stakeholder judgements, management targets and financing assumptions.Drifting Goals
5. Place-based by defaultUse transparent, evidence-informed territorial allocation criteria and strengthen delivery nodes where the evidence shows unmet needs. Any proposed minimum allocation must be validated, costed and applied consistently with appropriation and other applicable laws.Success to the Successful
6. Orchestrate, do not commandCoordination bodies convene, inform and escalate; statutory decisions stay with the mandated agency.Escalation; the Big Man
BIRD 2026–2035 · Chapter 7Page 4
Chapter 7

7.1 What the Evidence Says

Policy recommendations are only as credible as the patterns beneath them. Table 7.2 lists the six patterns, drawn from official statistics and the Validation Survey, that shape the recommendations in Sections A to D. Survey results are stakeholder judgements, not official baselines. They are used to set priorities and to test the roadmap's logic, consistent with the evidence contract in Chapter 1.

Six patterns that shape policy

Table 7.2. Evidence patterns and their policy implications
PatternEvidencePolicy implication
1. Growth is positive; the target path needs calibrationReported GRDP growth was 5.0% in 2025 and 2.7% in the 2024 release; the five-province 2025 base cited by MTIT is ₱266.59B. The illustrative path to ₱550B produces approximately 7.5% annual growth only under comparable series and price-basis assumptions, which B1 must verify.Publish an annual growth path; treat ₱550B as a stretch target with explicit assumptions (B1).
2. Institutions, not assets, are the constraintThe survey-based readiness measures were lowest relative to the other diagnostic dimensions across the clusters. A model chaining readiness through the value system estimates about 16% throughput, or 11.5% when the modelled governance factor is applied; these are analytical outputs, not observed conversion rates for real investment projects.Prioritise institutional and delivery reforms over new incentives (A1–A3, B2).
3. Enablers bind the systemEnablers: readiness 3.33, urgency 4.04; the widest gap (0.71) of any cluster. Infrastructure deficits (risk 17.41 of 25) and literacy (18.19) are the top-rated weaknesses.Sequence infrastructure, power and skills ahead of scale-up (A4, B4, B5).
4. Delivery capacity leaks valueUnderspending is rated a 16.85 of 25 risk. At an illustrative 80% execution rate, ₱28B of a ₱140B programme would remain unexecuted; that is a financial scenario, not a measured forecast of lost output.Link budget releases to execution and readiness (B2).
5. Geography concentrates attention53.4% name Maguindanao del Norte as the priority node, while 61.1% say Tawi-Tawi holds the most trapped value. No respondents came from Basilan or Tawi-Tawi.Set allocation floors and island delivery nodes; repeat validation with island quotas (B3, D2).
6. Stakeholders want transparency and parallel reform57.5% choose transparency as the critical governance loop; 57.5% want institutional, fiscal and regulatory reform in parallel; 87.5% support blended finance.Public dashboards, a agreed governance body and blended de-risking instruments (A2, C3, D2).

Sources: PSA-RSSO BARMM (2025); MindaNews (2026); MTIT (2026a); BIRD Validation Survey (2026). Weakness risk = Impact × Likelihood (0–25); threat vulnerability index = Impact² × Likelihood / 25 (0–5), per the canonical platform formulas. Missing answers are treated as missing, not zero.

BIRD 2026–2035 · Chapter 7Page 5
Chapter 7

Readiness and urgency by cluster

Figure 7.1 shows the core systems finding in one view. In every cluster, stakeholders judge the work urgent but institutions not ready. The gap is widest in the Enablers cluster, the cluster through which every other cluster's output must pass. This is the empirical basis for Rule 1 and for placing infrastructure, energy, digital connectivity and human capital at the front of the policy agenda.

Readiness versus urgency by BEIE cluster Dumbbell chart on a 3.0 to 4.2 scale. Foundations readiness 3.45, urgency 3.70. Transformers 3.40 and 3.69. Enablers 3.33 and 4.04. Connectors 3.61 and 3.94. Financiers 3.55 and 3.88. Operating systems 3.58 and 3.93. 3.03.253.53.754.04.25 FoundationsTransformersEnablersConnectorsFinanciersOperating systems gap 0.71 ReadinessUrgency
Figure 7.1. Mean readiness and urgency by BEIE cluster (1–5 scale). Enablers has the lowest readiness and highest urgency; the gold bar marks the widest gap. Source: BIRD Validation Survey (2026), n = 63–73 per item.
Table 7.3. Readiness, confidence and urgency by cluster
ClusterReadinessConfidenceUrgencyUrgency − readiness
Foundations3.453.693.700.25
Transformers3.403.603.690.29
Enablers3.333.704.040.71
Connectors3.613.863.940.33
Financiers3.553.783.880.33
Operating systems3.583.853.930.35
Systems reading. Stakeholders asked to rank budget priorities chose Foundations first (40.8%) and Enablers last but one (8.5%), while the readiness data identify Enablers as the binding cluster. The two views are reconciled, not overruled: Enablers investments are justified and sequenced by the Foundations pipeline they unlock, such as farm-to-market roads, cold chain and power for agro-processing (Recommendation B4).
Chapter 7

7.1.3 Evidence-to-Policy Traceability

Evidence-to-policy traceability. The recommendations below are not a separate strategy. They respond to specific findings in Chapters 1–6: Chapter 1 establishes the legal and territorial scope; Chapter 2 diagnoses interdependent cluster constraints and systems archetypes; Chapter 3 selects IEDS and identifies leverage points; Chapter 4 defines how performance should be measured; Chapter 5 connects capabilities to operational and economic outcomes; and Chapter 6 identifies delivery, budget, governance and MEL requirements. Where survey values appear, they are stakeholder-validation evidence (76 consented responses), not official administrative baselines.
Table 7.3A. Traceability from preceding chapters to policy action
Evidence baseFinding carried into Chapter 7Policy response
Chapter 1: legal anchors and scopeInvestment policy must operate within the Bangsamoro Organic Law, Administrative Code and applicable national frameworks, using the defined post-Sulu geography.A1–A3: legal concordance and clear institutional boundaries; B1 and B3: consistent geography.
Chapter 2: BEIE diagnosticsFive clusters and cross-cutting operating systems interact; constraints include infrastructure, human capital, institutional readiness and standards.A4–A6, B4–B5: address binding dependencies, not isolated sector symptoms.
Chapter 3: IEDS and leverage pointsIEDS is selected as the integrated strategy; enablers must be sequenced with value addition, market access and finance; archetypes warn against quick fixes and duplicated authority.A2–A3 and C1–C3: align governance, project preparation, financing and corridors with the IEDS.
Chapter 4: KPI architectureIndicators require defined owners, sources, time periods and calibration; survey-derived diagnostics are not official baselines.B1 and D3: one version-controlled register and consistent evidence labelling.
Chapter 5: causal BSC and BIF-NetCapabilities enable processes; processes create investor/community value; value should then appear in realised investment and financial outcomes.A3, C4–C5 and D5: case management, aftercare, accurate investor information and a results-chain dashboard.
Chapter 6: PAPs, financing and MELImplementation depends on phases, budget execution, named owners, dependency tracking and quarterly/annual learning cycles.B2–B5, C1–C3 and D4–D5: readiness-gated delivery, financing transparency, risk triggers and public reporting.
BIRD 2026–2035 · Chapter 7Page 6A
Chapter 7

A. Policy and Institutional Enablers

The policy stack contains instruments with different legal status: the Investment Code is a working legislative draft; the BIF-Net Executive Order is proposed; the Investors’ Guidebook is an informational and procedural resource; and the 2026 Strategic Investment Priority Plan is a national instrument cited in the evidence base. Their status must be verified with the relevant authorities before any issuance, enactment or public promise. The aim of Section A is to create one coherent investment system without treating a draft, an administrative instrument, a national plan and an investor guide as legally equivalent.

A.1 Legislative agenda for the first elected Parliament

Table 7.4. Priority instruments, status and recommended action
InstrumentStatus (October 2026)Recommended actionLP
Bangsamoro Investment Code (BIC)Draft as of 22 April 2026 (MTIT, 2026b)Enact a harmonised Code: incorporate RA 12066 (CREATE MORE) by reference rather than restating it; state the investment-capital line between BBOI and FIRB approval; add cost-benefit and clawback rules; correct drafting defects. See A2 for the council.LP3
Bangsamoro Board of Investments Act (Parliament Bill No. 409)Filed November 2025 in the interim Parliament (MindaNews, 2025)Merge into the BIC or refile, so that BBOI's mandate and the Regional Investment Priorities Plan are set in one statute, not two.LP3
Proposed BIF-Net Executive OrderDraft, 2026Use as the interim administrative framework only after reconciling its Council, Secretariat and Green Lane provisions with the Code; retain safeguards that preserve statutory permitting, registration and incentive powers.LP3
Investors’ GuidebookExisting investor-facing resource; version and content controls need confirmationRevise as a maintained service product tied to approved rules, a controlled baseline register and verified agency procedures; it must not create entitlements or substitute for law.LP3
Bangsamoro Forestry Code; MENRE-MILG JMC No. 2026-01Code before committee; JMC draftEnact and sign in the first year, with community benefit-sharing and FPIC safeguards before any carbon transaction.LP5
PPP frameworkDeferred by BIC Sec. 31Enact a Bangsamoro PPP and viability-gap funding framework, aligned with the national PPP Code, so the ₱120–160B envelope can lever private capital.LP2, LP4
2026 SIPP (MO No. 47)In force (Office of the President, 2026); BARMM list covers Halal Tourism and Islamic bank investment operations onlyPrepare an evidence-backed submission to widen the BARMM-specific list at the next SIPP review, using the BIRD sector diagnostics.LP1, LP4

Status reflects the documents in the BIRD evidence base and public reporting; bills not enacted by the interim Parliament should be checked with the Parliament Secretariat for refiling requirements.

A1
Complete a legally harmonised Investment Code before enactment. Direct MTIT, BBOI, BEZA, BPDA, MFBM and the Office of the Chief Minister to prepare a clean legislative master with one numbering system, consistent definitions, reconciled institutional mandates, and a provision-by-provision legal review. The uploaded draft dated 22 April 2026 contains duplicated or conflicting section numbering, overlapping alternative clauses and incomplete text; these are substantive risks to interpretation, not editorial issues. Harmonise the Code with the Bangsamoro Organic Law, Administrative Code and applicable national rules, including RA 12066 (CREATE MORE), without restating or expanding national incentives beyond BARMM’s lawful authority. Specify the RIPP process and how it uses BIRD evidence, while preserving the relevant national SIPP and statutory approval routes. For incentives, define jurisdiction and approval thresholds, eligibility, monitoring of actual performance, fiscal cost-benefit review, due process and legally available suspension/recovery remedies. Owner: MTIT and BBOI with BEZA, BPDA, MFBM and OCM; Parliament to determine the legislative route. Horizon: clean master and legal concordance before refiling; target enactment during the first legislative year, subject to legislative process. Evidence: Chapters 1 and 3 identify the legal anchors and investment-priority logic; Chapter 2 identifies institutional and capacity constraints; Chapter 4 requires measurable results; Chapter 6 requires funded and accountable implementation. The survey’s 44.9% regulatory-priority response is a stakeholder signal, not legal proof.
BIRD 2026–2035 · Chapter 7Page 7
Chapter 7

A.2 Resolve council overlap and harmonise the institutional model

The draft Investment Code proposes a Bangsamoro Investment Development Council (BIDC), the proposed BIF-Net Executive Order establishes a BIF-Net Council, and Chapter 6 describes a Bangsamoro Investment Command Center (BICC) as an implementation and performance-management hub. Their functions and reporting relationships overlap in the current drafts, creating a risk of duplicate approvals, unclear accountability and competing data systems. The evidence from Chapters 2–3 on institutional bottlenecks and escalation supports resolving this overlap before operationalisation. The final design must be settled through legal review against the Bangsamoro Organic Law, Administrative Code and other applicable laws; an Executive Order must not displace powers that require legislation or are assigned by statute.

A2
Resolve institutional overlap and adopt one coordinated operating model. Subject to legal review, use one policy council for cross-government investment coordination, one BIF-Net network for inter-agency facilitation, and one designated Secretariat/operating office within MTIT–BOI for case management, data and aftercare. Determine whether BIDC and the BIF-Net Council should be merged, reconstituted or assigned distinct non-duplicative functions in the Code and EO. Define the BICC's status as a function or operating unit—not an additional approval body—unless a separate legal basis is established. Preserve BBOI, BEZA, ministry, national-agency and LGU statutory decision rights. Add private-sector and LGU participation with conflict-of-interest, confidentiality and recusal rules. Owner: OCM and MTIT, with legislative counsel and relevant agencies. Horizon: reconcile in the amended EO and Code package before final issuance/enactment.
BIRD 2026–2035 · Chapter 7Page 8
Chapter 7

A.3 BIF-Net as ecosystem orchestrator

BIF-Net should act as the facilitation and orchestration layer for the IEDS, not as a new licensing or incentive-granting authority. Consistent with the proposed EO, its core functions are to provide a “No Wrong Door” entry point, maintain a central case registry, assign a lead investment officer, coordinate referrals and parallel processing where lawful, monitor agreed service standards, escalate unresolved inter-agency bottlenecks, and provide investor aftercare. Chapters 5–6 require the same operating system to connect the investment pipeline with the Balanced Scorecard (BSC), Programs–Activities–Projects (PAPs), budgets and MEL. Any cluster councils or coordination forums should be subordinate coordination mechanisms, not additional statutory approval gates.

BIF-Net orchestration architecture Policy tier: investment-policy coordination council with structured stakeholder input and a national interface. Orchestration tier: BIF-Net Secretariat/operating office within MTIT–BOI, subject to final legal design. Execution tier: five BEIE cluster councils. A cross-cutting review layer and provincial investment nodes sit beneath. Private sector boardChambers, banks, CSOs Investment policy councilRoles reconciled in law National interfaceFIRB, BOI, IGRB, NGCP/ERC BIF-Net Orchestration Office (MTIT-BoI)Pipeline, data, case pipeline, lawful Green Lane coordination, aftercare and grievances FoundationsTransformersEnablersConnectorsFinanciers Lead: MAFARLead: MTITLead: MPWLead: MTIT–BEZALead: MFBM Cross-cutting review layerMoral governance · peace and security · human capital · tourism · green economy Provincial investment nodesLanao del Sur · Maguindanao del Norte · Maguindanao del Sur · Basilan (Lamitan) · Tawi-Tawi · SGA · Cotabato City
Figure 7.2. Proposed BIF-Net orchestration architecture. The legally constituted policy body provides direction; the Secretariat coordinates cases and data; technical/cluster forums resolve dependencies; and territorial nodes support local delivery. Final governance arrangements must be reconciled with the Investment Code and existing law. Statutory permits, registrations and incentive decisions remain with the mandated authority.
Table 7.5. BEIE cluster councils
Cluster councilPublic lead (co-leads)Agenda focus
FoundationsMAFAR (MENRE, SPDA, MIPA)Feedstock, land tenure and FPIC, seaweed, rubber, fisheries, renewable supply
TransformersMTIT (BEZA, MOST, halal authority)Halal processing, testing, Matanog Halal Park, value addition
EnablersMPW (MOTC, MENRE-Energy, MHSD, MBHTE, BPDA)Roads, ports, power, digital, skills; PPP sequencing
ConnectorsMTIT and BEZA (MOTC; BIMP-EAGA desk)Trade facilitation, Polloc Freeport, corridors, tourism circuits
FinanciersMFBM (Darul-Ifta advisory; CSEA; BSP as observer)Islamic finance, blended finance, MSME credit, takaful
A3
Operationalise BIF-Net through enforceable coordination protocols and a traceable case-management service. Specify case stages from inquiry and completeness review through agency referrals, registration/incentive decisions by the legally mandated authority, permitting, implementation, closure and aftercare. Give each case a unique reference, named lead officer, participating-agency list, next action, responsible office, applicable statutory timeline and escalation route. Publish service standards for BIF-Net actions—such as acknowledgement, assignment, status updates and escalation—separately from statutory approval periods. The Green Lane may coordinate and expedite processing where permitted by law; it must not waive required permits, consultations, environmental and labour safeguards, taxes, or other legal obligations. Establish privacy, access control, audit-trail, data-sharing, complaints and continuity rules for the digital system. Owner: MTIT–BOI Secretariat with member agencies and LGUs. Horizon: IRR, Rules of Procedure and Green Lane Guidelines before full operation.
BIRD 2026–2035 · Chapter 7Page 9
Chapter 7

A.4 Standards, finance and energy institutions

Halal assurance (LP1). International buyers do not buy a label; they buy the credibility of the body behind it. Halal certification weakness is rated a 15.65 of 25 risk and standards recognition a 2.77 of 5 threat. The policy priority is institutional: a certification authority (the Bangsamoro Halal Board referred to in Chapter 6) with a statutory basis, an accreditation path aligned with OIC/SMIIC requirements for halal certification bodies, laboratory capacity in Cotabato City and Marawi, and a mutual-recognition sequence that starts with BIMP-EAGA partners and extends to GCC markets as accreditation matures.

A4
Put halal assurance on a statutory and accredited footing. Owner: halal certification authority with MTIT and MOST. Horizon: statutory basis and accreditation plan in Phase 1; first mutual-recognition arrangement in Phase 2; SMIIC-aligned recognition by 2035.

Islamic finance (LP4). Banking regulation is a national function: the Bangko Sentral ng Pilipinas licenses and supervises Islamic banks under RA 11439. The Bangsamoro role is to build demand, pipeline, Shariah governance capacity and public-sector use of Islamic instruments. Among respondents, 72.3% consider a coordinating Islamic finance authority essential and a further 18.5% support one once basic banking is strengthened. Their top actions are financial literacy (29.4%), human capital (23.5%) and regulatory clarity, including tax neutrality (22.1%).

A5
Establish a Bangsamoro Islamic finance coordination council. Located in MFBM, with Bangsamoro Darul-Ifta advisory and a working protocol with BSP. Mandate: literacy and talent programmes, a sukuk-ready project pipeline, takaful for climate and agricultural risk, and advocacy on national tax-neutrality rules. It does not license or supervise institutions. Owner: MFBM. Horizon: Phase 1.

Energy (LP2). The DOE and MENRE signed a transition agreement in 2026 to devolve power-sector regulation and development functions to MENRE in phases. Devolution creates an opportunity and a capacity risk. Reported electrification also depends heavily on definition: about 40% of potential household connections in BARMM electric cooperative areas (NEA, 2023), against 67.52% of households region-wide at end-2025 in the devolution announcement. Transmission links such as the Zamboanga–Basilan interconnection fall under the grid operator's franchise and ERC regulation, so they require a national interface rather than regional procurement alone.

A6
Make energy devolution investable. Adopt one household-electrification metric for all BIRD reporting; build MENRE's regulatory and planning capacity on a published schedule; prioritise electric cooperative turnaround and island mini-grids; and coordinate transmission projects with NGCP, ERC and DOE through the national interface. Owner: MENRE. Horizon: Phase 1, reviewed annually.
Why these are institutional recommendations. Each of A4–A6 strengthens a body that must exist and perform before incentives can work. Granting incentives to halal exporters without a recognised certifier, or to agro-processors without reliable power, would reproduce the Fixes that Fail pattern documented in Chapter 2.
BIRD 2026–2035 · Chapter 7Page 10
Chapter 7

B. Planning, Budgeting and Territorial Delivery

B.1 One set of baselines

Since the Supreme Court decision of 9 September 2024, Sulu is outside BARMM (Supreme Court of the Philippines, 2024). Several official series in circulation still describe the region as it was before that decision, and different documents use different definitions for the same indicator. Until baselines are rebased and owned, targets can be met or missed by arithmetic alone. Table 7.6 lists the reconciliations required before the KPI register is adopted.

Table 7.6. Baseline reconciliation required before adoption
IndicatorValues in circulationIssueRequired action
GRDP level₱299.5B (2024); ₱266.59B (2025, five provinces, per MTIT citing PSA)The 2024 figure is close to the pre-exclusion series; Sulu was about 16% of 2022 GRDP.Adopt the PSA five-province series; restate the ₱550B path (about 7.5% a year).
GRDP growth, 20242.7% (April 2025 release); about 3.4% in 2026 reportingRevision or change of territorial basis.Confirm with PSA-RSSO BARMM.
Poverty incidence34.8% (first semester 2023); 23.5% (full-year 2023, families)Different reference periods. On the full-year measure, the <25% target for 2030 is already met.Use full-year five-province estimates; recalibrate the 2030 and 2035 targets.
Population4.54 million; 5.69 million in some planning toolsThe higher figure appears to include Sulu.Use 4.54 million until the next official update.
Household electrification~39–40% (NEA, EC areas); 67.52% (DOE–MENRE, end-2025); ~75% (planning tools)Three definitions and denominators.Adopt one metric and owner (A6).
Phase 2 and 3 boundariesChapter 6 and the KPI architecture use Phase 1 2026–2028, Phase 2 2029–2031 and Phase 3 2032–2035; some platform views show different boundaries.Adopt the Chapter 4–6 phase definitions as the canonical schedule, then align the platform, dashboards, workplans and all public versions. Preserve an approved change log if an authorised review changes a boundary.
Investment requirement₱1.55–1.77 trillion at ICOR 3.5–4.0Implies an output increment of about ₱443B, larger than the constant-price gap to ₱550B.Reconcile the output increment, price basis and ICOR method; publish assumptions and sensitivity.

Sources: PSA-RSSO BARMM (2023, 2025); PSA (2024); MindaNews (2026); MTIT (2026a); NEA (2023); Context.ph (2026). The reconciliation does not change the strategy; it changes the numbers used to judge it.

B1
Create a canonical baseline and target register. BPDA, with PSA-RSSO BARMM and each official data owner, should maintain one controlled register with each KPI’s definition, unit, geographic coverage, reference period, price basis where relevant, disaggregation, baseline, target path, source, validation method, update frequency and accountable data owner. Reconcile the five-province geography and include the SGA and Cotabato City where the indicator’s definition supports it. Resolve the GRDP, poverty, population and electrification discrepancies listed in Table 7.6; do not select a value solely because it yields a preferred target. Use Chapter 6’s phase boundaries—2026–2028, 2029–2031 and 2032–2035—consistently across the narrative, dashboard and annual plans. Changes must be versioned with a dated rationale and approved through the legally designated process. Owner: BPDA with PSA-RSSO BARMM, MTIT–BOI and relevant ministries. Horizon: register approved before formal BSC scoring; continue revisions through controlled releases.
BIRD 2026–2035 · Chapter 7Page 11
Chapter 7

B.2 Budgeting for delivery, not intention

A plan's value is the portion of it that becomes output. Underspending is one of the highest-rated weaknesses in the survey (16.85 of 25), and infrastructure cost overruns are among the highest-rated threats (3.07 of 5). Two budgeting reforms address both. First, tag every budget line that funds a BIRD programme to its BEIE cluster and leverage point, so that the Parliament can see the investment logic in the appropriations. Second, align later-phase releases with verified project readiness, procurement and delivery gates, as Chapter 6 proposes. Any central contingency reserve should be separately justified, costed and authorised through the budget process.

The first-year action plan illustrates concentration risk: the chapter’s illustrative budget table assigns ₱2.0 billion of ₱2.063 billion to one transmission project, while the remaining institutional actions are much smaller. These are planning figures that should be reconciled to approved appropriations and current project estimates before execution. Protect critical institutional and project-preparation activities from routine reallocation through lawful budget tagging, readiness gates and transparent variance reporting; do not imply that this chapter can ring-fence funds outside the appropriations process.

B2
Link expenditure to readiness, delivery and results. Tag BIRD-related budget items by PAP, BEIE cluster and leverage point; connect release decisions to approved appropriations, project readiness, procurement milestones and verified outputs; and report quarterly on obligations, disbursements, physical progress, cost variance and delays. Protect essential institutional and project-preparation work through the formal budget process. Treat the BSC’s >90% execution target as a management target, not a substitute for output verification: high expenditure without output should trigger review. Any 20% contingency reserve or other funding rule must be separately costed, authorised and reflected in the budget. Owner: MFBM with BPDA and implementing agencies. Horizon: 2027 budget cycle onward.
B4
Sequence Enablers by the Foundations pipeline they unlock. Prioritise farm-to-market roads, cold chain, port upgrades and power for named agro-processing and fisheries projects, rather than infrastructure in the abstract. Stakeholders favour physical connectivity (58.9%) and market-access assets (32.9%) over digital backbones (8.2%) as the first priority. Owner: MPW and MAFAR through the Enablers council. Horizon: Phase 1 project list by Q3 2027.
B5
Close the skills gap with an industry compact. Functional literacy (18.19 of 25) and skills mismatch (16.96) are the top-rated human-capital weaknesses. MBHTE's technical-education arm, MOLE and cluster councils agree occupational skills plans tied to the investment pipeline, with employer co-design and placement targets. Owner: MBHTE and MOLE. Horizon: first plans in 2027; annual update.
A note on the target. Holding ₱550B as the 2035 GRDP goal is a strategic ambition, but the implied annual growth rate depends on whether the target and base use comparable current-price or constant-price series, geography and rebasing. The current illustrative calculation uses the cited ₱266.59B five-province 2025 base and produces approximately 7.5% annual growth under the stated assumptions; it should not be treated as a verified real-growth requirement until the price basis and official series are confirmed. The register (B1) should publish the reproducible calculation and annual path so that slippage is visible early.
BIRD 2026–2035 · Chapter 7Page 12
Chapter 7

B.3 Territorial delivery across the Bangsamoro

One model will not serve a mainland agro-industrial basin, a lake-and-highland province, a freshly organised Special Geographic Area, an administrative city and two island provinces. The territorial units for BIRD are the five provinces of Lanao del Sur, Maguindanao del Norte, Maguindanao del Sur, Basilan (excluding Isabela City) and Tawi-Tawi, together with the Special Geographic Area and Cotabato City. Two boundary facts matter for delivery. Basilan's provincial seat, Isabela City, lies outside BARMM, so BARMM-side delivery in Basilan should run through Lamitan and municipal centres, with a cross-boundary arrangement for port and logistics links through Isabela City and Zamboanga City. Sulu is now outside the region; it is a neighbour and corridor partner, not a delivery territory.

Table 7.7. Territorial delivery typology
UnitPrimary roleBinding constraints to addressDelivery node and instrument
Maguindanao del NorteHalal hub and freeport gatewayIndustrial land, power reliability, logistics to PollocPolloc Freeport; Matanog Halal Park; BEZA
Maguindanao del SurAgro-industrial basinFlooding, farm-to-market roads, tenureProvincial node in Buluan; agri-processing clusters
Lanao del SurEnergy, highland agriculture, Marawi servicesRehabilitation completion, watershed protectionMarawi node; Wao–Amai Manabilang corridor
BasilanRubber and aquaculture; peace-dividend provincePower interconnection, processing, cross-boundary logisticsLamitan node; Region IX coordination
Tawi-TawiMaritime gateway; seaweed; BIMP-EAGAShipping, cold chain, connectivity, island powerBongao node; seaweed processing; BIMP-EAGA trade facilitation
Special Geographic AreaMindanao land bridge; new municipalitiesBasic services, LGU capacity, tenureSGA node; LGU investment-readiness support
Cotabato CityAdministrative and commercial capitalUrban services, port, flood riskBIF-Net head office; services and logistics

The survey shows why an explicit rule is needed. Respondents name Maguindanao del Norte as the priority node (53.4%) but judge Tawi-Tawi to hold the most trapped value (61.1%), and 56.2% say Basilan and Tawi-Tawi serve different corridors and deserve equal weight. Left to habit, resources follow existing capacity; that is the Success to the Successful archetype.

B3
Implement a transparent, place-based delivery approach. Use provincial diagnostics and documented project readiness to allocate technical assistance, project preparation and enabling infrastructure. Prioritise appropriate delivery nodes for Bongao, Lamitan and the SGA, and establish lawful cross-boundary arrangements with Region IX for Basilan’s logistics links, noting that Isabela City is outside BARMM and Sulu is a corridor partner rather than a delivery territory. Chapter 6 proposes a 30% minimum allocation for lagging and island areas; validate the rationale, eligible expenditure base, territorial criteria and fiscal implications before adoption, and implement only through authorised plans and appropriations. The absence of Basilan and Tawi-Tawi respondents means the survey cannot be treated as direct representation of island-province preferences; validate through province-based consultation. Owner: MTIT–BOI with MILG, BPDA and LGUs. Horizon: Phase 1 framework and pilot nodes, subject to local readiness and funding.
BIRD 2026–2035 · Chapter 7Page 13
Chapter 7

C. Investment Mobilisation and Market Development

C.1 From incentives to investability

Incentives alone do not establish investability. A project also needs lawful registration and eligibility, secure site and tenure arrangements, predictable permitting, available infrastructure and power, credible market/offtake, appropriate safeguards, and risks that can be priced. The Code must align any regional incentive provisions with applicable national law and the jurisdiction of the relevant investment promotion agency; the Guidebook must explain actual eligibility rather than advertise incentives as automatic. BARMM's comparative advantages are its halal credibility, its Islamic finance potential and its BIMP-EAGA position. Investment mobilisation should convert these into a pipeline of prepared projects.

C1
Establish a project-preparation function and quality-controlled pipeline. Prepare priority projects through pre-feasibility, land/tenure and site due diligence, environmental and social safeguards, climate and conflict sensitivity, market/offtake testing, cost estimates and transaction advice. For every entry, record the sponsor, location, stage, dependencies, approvals required, capital need, financing status, risks and next decision. Use clear statuses—concept, under preparation, feasibility-complete, approval-ready, financing-committed, under construction and operating. Do not describe an opportunity as bankable or investment-ready until the evidence and responsible sponsor support that designation. Owner: MTIT–BOI with BPDA, sector agencies, LGUs and development partners. Horizon: facility design by Q4 2027 and an initial prepared-project cohort in 2028, subject to funding and readiness.

C.2 Market corridors and standards

Asked where to point the export effort, 52.1% of respondents chose BIMP-EAGA and UAE/GCC markets together, 35.6% BIMP-EAGA first and 12.3% UAE/GCC first. The two corridors have different entry conditions. BIMP-EAGA markets are near, culturally close and reachable with existing products; GCC markets pay more but require recognised standards and reliable logistics. The policy implication is a sequence within a parallel strategy: build volume and traceability in BIMP-EAGA now, while the standards work in A4 opens GCC access.

C2
Run a two-corridor market strategy. Prioritise BIMP-EAGA trade facilitation, Tawi-Tawi and Polloc logistics and buyer-supplier matching in Phase 1; develop GCC access through accredited halal certification and traceability as recognition is secured. Owner: MTIT with BEZA and the Connectors council. Horizon: Phase 1 for BIMP-EAGA; Phase 2 for GCC scale-up.

C.3 The capital stack

The Roadmap models a ₱120–160 billion investment envelope and an indicative 11–14× leverage requirement. These figures should be treated as planning assumptions until a costed financing plan and commitments are verified; they are not evidence that funds have been appropriated or that private capital is secured. The Validation Survey indicates stakeholder support for blended finance (87.5%), with preferences for infrastructure-scale instruments (56.3%), MSME access (25.0%) and risk mitigation (18.8%). These are preferences, not proof of bankability. The financing architecture should combine project preparation, clearly allocated public and private risks, development-finance guarantees where available, Shariah-compatible financing, MSME capital and climate/agricultural risk coverage, subject to mandates and market testing.

C3
Develop an auditable, blended and Shariah-compatible financing plan. For each priority programme/project, disclose the capital source, instrument, expected timing, financing gap, risk allocation, readiness status and responsible sponsor. Report public appropriations, signed commitments, indicative interest and aspirational mobilisation separately; define how the 11–14× leverage assumption is calculated and avoid counting the same capital twice. Establish first-loss, guarantee, sukuk, MSME-finance or takaful proposals only where a qualified financier and lawful operating arrangement are identified. Owner: MFBM with MTIT–BOI, project sponsors and prospective financing partners. Horizon: financing plan in Phase 1, updated quarterly as commitments change.
BIRD 2026–2035 · Chapter 7Page 14
Chapter 7

C.4 Aftercare, retention and reinvestment

The cheapest investment to attract is the next one from a firm already operating in the region. Reinvestment depends on how existing investors are treated: whether problems are solved, whether rules are stable and whether the government listens. The Balanced Scorecard target of investor satisfaction at 8.0 of 10 by 2035 has no baseline yet, and the investor information that exists is spread across separate documents and systems.

C4
Institutionalise investor aftercare and grievance resolution. Assign a case/account officer for facilitated and registered investors according to risk and service capacity; maintain a confidential channel for complaints and a de-identified systemic-issue log; track response, resolution and recurrence; and record actual versus pledged investment, employment and reinvestment using the proper agency data owner. Establish an investor-satisfaction baseline before claiming progress against the Chapter 5 target of 8.0/10 by 2035. Owner: designated BIF-Net Secretariat with BBOI, BEZA and relevant agencies. Horizon: phased start from 2027, with annual reporting.
C5
Rebuild the Investors’ Guidebook as a controlled, investor-facing service product. Publish a version date, content owner, change log and correction channel. For each investor pathway, state the responsible office, legal basis, eligibility, documents, fees where applicable, official processing time, sequence, referral route and escalation channel. Clearly distinguish statutory processing periods from BIF-Net service standards; explain Green Lane eligibility and the fact that facilitation does not waive legal requirements. Use the canonical baseline register (B1) and label opportunities as concepts, under preparation, finance-ready, approved, under construction or operational—never describe an unverified concept as an approved or bankable project. Owner: MTIT–BOI with BBOI, BEZA and member agencies. Horizon: first controlled digital edition in 2027 and updates when rules or agency procedures change, with a full annual review.
Table 7.8. Investment mobilisation measures and the leverage points they serve
MeasureLeverage pointPrimary clusterHeadline KPI affected
C1 Project preparation facilityLP2, LP3Enablers, TransformersAnnual investment approvals; realised investment
C2 Two-corridor market strategyLP1ConnectorsTotal exports
C3 Blended capital stackLP4, LP5FinanciersIslamic banking assets; leverage ratio
C4 Aftercare and grievance channelLP3Cross-cuttingInvestor satisfaction; reinvestment
C5 Verified investment informationLP3Cross-cuttingInvestor inquiries converted to registrations
Green economy revenue (LP5). Stakeholders favour pursuing payments for ecosystem services, carbon credits and eco-tourism fees together (53.5%). The binding conditions are legal: the Forestry Code, the JMC and community benefit-sharing rules (A1). Carbon transactions should not proceed ahead of those safeguards, whatever the market timing.
BIRD 2026–2035 · Chapter 7Page 15
Chapter 7

D. Governance of the Way Forward

D.1 Transition-proofing the roadmap

The first regular Bangsamoro Parliament was elected on 14 September 2026. No party won a majority: the Bangsamoro Federalist Party and the United Bangsamoro Justice Party lead with close seat counts, so the Chief Minister will be elected through coalition (Reuters, 2026). A ten-year roadmap that belongs to one administration will not survive its successor. BIRD's continuity therefore depends on being adopted as a shared framework rather than a partisan programme.

D1
Adopt BIRD as a shared, cross-party investment framework. Present BIRD to the first session for endorsement by resolution; feed it into the next Bangsamoro Development Plan as the investment chapter; and require any change to headline targets to pass through the baseline register and the agreed governance body with a published rationale. Owner: OCM, MTIT and BPDA. Horizon: endorsement within the first parliamentary year.

D.2 Learning, evidence and review

Respondents prefer quarterly adaptive review (51.4%) over annual review (31.4%). The current evidence base also has known limits. About three-quarters of respondents are government-affiliated, only 11 of 76 (14.5%) are from the private sector, and Basilan and Tawi-Tawi returned none. Cotabato City (27) and Maguindanao del Norte (22) supply most responses. Findings about the island provinces are therefore judgements made about them, not by them.

D2
Run a second validation wave with quotas. In 2027, repeat validation with minimum quotas for Basilan, Tawi-Tawi, the SGA and the private sector, using province-based workshops where online access is weak. Remove response options that refer to territory outside BARMM. Owner: MTIT-BoI with BPDA. Horizon: before the first annual BSC assessment.
D3
Apply one evidence and reporting contract across the Roadmap, BIF-Net and investor information. Keep (1) official statistics and administrative records, (2) stakeholder-validation survey results, and (3) management targets, forecasts and financing assumptions visibly separate. Every published indicator should show source, date, geography, definition and status; survey measures should be labelled as perceptions and not administrative baselines. Link BIF-Net case data and Guidebook content to the controlled register where appropriate, while protecting confidential business information and personal data. Report the conversion chain separately: inquiry → qualified pipeline → registration/approval → permits/facilitation → realised investment → jobs, exports and wider outcomes. Owner: BPDA and MTIT–BOI with official data owners. Horizon: immediate design rule; continuous application.
BIRD 2026–2035 · Chapter 7Page 16
Chapter 7

D.3 Systemic risk triggers

Table 7.9. Highest-rated threats and their policy triggers
Threat (VI, 0–5)Early-warning indicatorPre-agreed response
Security incidents (3.20)Incidents in investment zones; investor withdrawalsActivate MPOS investor-security protocol; targeted risk cover through C3
Climate change (3.14)Flood and drought losses to agriculture and infrastructureClimate screening for all projects; takaful and contingency release
Infrastructure cost overruns (3.07)Cost variance >15% on priority projectsIndependent review before additional release (B2)
Drifting goals (3.03)Unlogged target changes; KPI variance >15% for two quartersEscalation to the agreed governance body; public variance note (B1)
National coordination (2.91)Pending national permits beyond service standardsEscalation through the national interface and IGRB
Political transition (2.85)Leadership change; budget reallocation away from tagged linesCross-party endorsement (D1); ring-fenced institutional actions (B2)
Trigger governance rule. Thresholds in Table 7.9 are proposed management triggers for review, not automatic legal sanctions or evidence of causation. Each trigger should name the validating data source, accountable reviewer, response authority, review deadline and closure evidence. For example, a cost variance should first be reconciled to approved scope, inflation, procurement and engineering data before any funding decision; a permit delay should be escalated through the lawful inter-agency route.
D4
Adopt the trigger table as part of the MEL protocol, reviewed quarterly by the designated investment coordination body. For each trigger, document the evidence source, validation step, responsible agency, response authority and closure criteria. Owner: BIF-Net Secretariat with BPDA and relevant agencies. Horizon: after adoption of the operating protocol.
D5
Publish an annual, evidence-checked BIRD performance report and dashboard. Report KPI baselines and targets, PAP status, budget and physical progress, investment pipeline stages, processing performance, realised investment, outcome indicators and recurring systemic issues. Publish aggregate information only where disclosure is lawful; protect commercially confidential applications, personal data and security-sensitive information. Explain revisions and missed milestones rather than silently changing target paths. Owner: MTIT–BOI and BPDA with data owners. Horizon: first consolidated report in 2027, then annually; quarterly operational updates where data are validated. Survey support for transparency (57.5%) is a stakeholder signal, not a substitute for privacy and disclosure rules.
BIRD 2026–2035 · Chapter 7Page 17
Chapter 7

7.2 Consolidated Recommendation Matrix

Table 7.10. Twenty-one recommendations at a glance
IDRecommendationOwnerHorizonLPCluster
A1Complete and enact a harmonised Bangsamoro Investment CodeMTIT, BBOI, OCMFirst legislative year, subject to processLP3Cross-cutting
A2Resolve council overlap; establish one coherent governance modelOCM, MTITBefore final issuance/enactmentLP3Cross-cutting
A3Operationalise BIF-Net case management and lawful escalationMTIT-BoIQ2 2027LP3All
A4Statutory, accredited halal assuranceHalal authority, MTIT, MOSTPhase 1–2LP1Transformers
A5Islamic finance coordination councilMFBMPhase 1LP4Financiers
A6Make energy devolution investableMENREPhase 1LP2Foundations, Enablers
B1Canonical baseline and target register, version-controlledBPDA, PSA-RSSOQ4 2027LP3Cross-cutting
B2Link budget to readiness, outputs and resultsMFBM, BPDA2027 budgetLP3All
B3Evidence-led territorial delivery and island nodesMTIT-BoI, MILGPhase 1LP2, LP3Enablers
B4Enablers sequenced by Foundations pipelineMPW, MAFARQ3 2027LP2Enablers
B5Industry skills compactMBHTE, MOLE2027LP2Enablers
C1Project preparation function and quality-controlled pipelineMTIT-BoI, BPDAQ4 2027LP2, LP3Enablers, Transformers
C2Two-corridor market strategyMTIT, BEZAPhase 1–2LP1Connectors
C3Auditable blended and Shariah-compatible financing planMFBM2027–2028LP4, LP5Financiers
C4Investor aftercare and grievance resolutionBIF-Net officeQ2 2027LP3Cross-cutting
C5Controlled Guidebook and verified investor informationMTIT-BoI2027LP3Cross-cutting
D1Cross-party endorsement of BIRDOCM, MTIT, BPDAFirst yearLP3Cross-cutting
D2Second validation wave with quotasMTIT-BoI, BPDA2027LP3Cross-cutting
D3Common evidence and reporting contractBPDA, MTIT-BoIContinuousLP3Cross-cutting
D4Systemic risk trigger tableBIF-Net officeQ1 2027LP3Cross-cutting
D5Evidence-checked public reporting and dashboardMTIT-BoI, BPDA2027LP3Cross-cutting

LP1: standards and certification integrity; LP2: infrastructure, energy and connectivity; LP3: governance, information and investor confidence; LP4: Islamic finance ecosystem; LP5: green-economy revenue and safeguards. LP3 is prominent because Chapters 2–3 identify institutional throughput as a binding constraint. This is a prioritisation judgement supported by the roadmap’s diagnostics, not a claim that other leverage points are dispensable.

BIRD 2026–2035 · Chapter 7Page 18
Chapter 7

7.3 The Way Forward

The first 180 days

The period from the new Parliament's first session to mid-2027 decides whether BIRD becomes the region's investment framework or one document among many. The sequence below asks for decisions, not large budgets.

Table 7.11. Decisions for the first 180 days (November 2026 – April 2027)
WindowDecisionRecommendations
Days 1–30Brief the Chief Minister and cabinet; designate the proposed BIF-Net Secretariat/operating office subject to the final EO; agree the legal design for the policy council and operating network.A2, D1
Days 31–60Complete legal review and issue the amended BIF-Net EO if within executive authority; finalise/refile the Investment Code and Forestry Code through the lawful legislative process; execute JMC No. 2026-01 only after required approvals.A1, A3
Days 61–90Start the baseline register with PSA-RSSO; tag the 2027 budget; adopt the trigger table.B1, B2, D4
Days 91–120Stand up the Transformers, Enablers and Financiers councils; open the Bongao and Lamitan nodes; set up aftercare.A3, B3, C4
Days 121–180Launch the second validation wave; scope the project preparation facility; publish the first quarterly dashboard.C1, D2, D5
BIRD 2026–2035 · Chapter 7Page 19
Chapter 7

Policy review calendar to 2035

2027 — Foundation year. Complete legal harmonisation of the Code and BIF-Net instruments; establish the agreed governance arrangement; approve the baseline register; conduct the first annual BSC assessment and publish a validated performance report, subject to legislative and budget processes.
2028 — End of Phase 1. Gate review of Phase 1 deliverables before Phase 2 releases; first prepared projects reach financing; halal accreditation plan in execution.
2030 — Mid-term review. External evaluation; recalibration of targets on rebased data; decision on whether BIF-Net remains a network or becomes an attached agency.
2031 — Second regular Parliament. Renewed cross-party endorsement; SIPP submission for an expanded BARMM list; review of incentive effectiveness.
2035 — Terminal assessment. Evaluation against the Balanced Scorecard; design of the successor roadmap.

Closing statement

RulesInstitutionsInformationDelivery capacityInvestable projectsCapitalJobs and resilience

BIRD 2026–2035 does not ask BARMM to rely on a single sector, one incentive or one administrative body. It recommends a coherent sequence: use the evidence in Chapters 1–2 to identify constraints; apply the IEDS and leverage points in Chapter 3; maintain the calibrated KPIs and baseline discipline in Chapter 4; manage the causal pathways and Balanced Scorecard in Chapter 5; and implement the budgeted PAPs and MEL cycle in Chapter 6. The Investment Code should provide lawful and durable authority; the BIF-Net EO and rules should organise lawful inter-agency facilitation; the Investors’ Guidebook should explain verified requirements and opportunities; and the Roadmap should align all three with territorial priorities, financing and measurable results. This architecture will build investor confidence only if responsibilities are clear, commitments are funded, legal safeguards are respected and performance is reported against verifiable evidence.

Continue reading
Subject Index

Open Subject Index
BIRD 2026–2035 · Chapter 7Page 20
Back matter

References

BIRD Validation Survey. (2026). Consented responses, 3–20 August 2026 (n = 76) [Data set]. BOI-MTIT and AS Strategic Insights.

Bangsamoro Planning and Development Authority. (2023). 2nd Bangsamoro Development Plan 2023–2028. BARMM Government. https://knowledge.bpda.bangsamoro.gov.ph/

Context.ph. (2026, June 3). DOE transfers power sector function to BARMM-MENRE under new transition deal. https://context.ph/2026/06/03/doe-transfers-power-sector-function-to-barmm-menre-under-new-transition-deal/

Meadows, D. H. (1999). Leverage points: Places to intervene in a system. Sustainability Institute.

MindaNews. (2025, November 11). More powers for Bangsamoro investment agency sought. https://mindanews.com/business/2025/11/more-powers-for-bangsamoro-investment-agency-sought/

MindaNews. (2026, April 24). Mindanao average economic growth rate in 2025 above national rate. https://mindanews.com/business/2026/04/mindanao-average-economic-growth-rate-in-2025-above-national-rate/

Ministry of Trade, Investments and Tourism–BARMM. (2026a). Investors’ Guidebook for BIF-Net. Bureau of Investments.

Ministry of Trade, Investments and Tourism–BARMM. (2026b). Draft Bangsamoro Investments and Incentives Code (working draft as of 22 April 2026). Bureau of Investments.

Ministry of Trade, Investments and Tourism–BARMM. (2026c). Proposed Executive Order establishing the Bangsamoro Investment Facilitation Network (BIF-Net). Bureau of Investments.

National Electrification Administration. (2023). NEA hopes I-PURE projects will boost Mindanao electrification rate. https://nea.gov.ph/

Office of the President of the Philippines. (2026). Memorandum Order No. 47: Approving the 2026 Strategic Investment Priority Plan.

Philippine Statistics Authority. (2024). 2023 full year official poverty statistics. https://psa.gov.ph/

Philippine Statistics Authority–RSSO BARMM. (2023). Lanao del Sur's economy posts 5.4 percent in 2022 [Provincial product accounts, 2018–2022]. https://rssobarmm.psa.gov.ph/

Philippine Statistics Authority–RSSO BARMM. (2025). BARMM's economy expands by 2.7 percent in 2024 (Reference No. 2025-033). https://rssobarmm.psa.gov.ph/

Republic Act No. 11054. (2018). Organic Law for the Bangsamoro Autonomous Region in Muslim Mindanao.

Republic Act No. 11439. (2019). An Act Providing for the Regulation and Organization of Islamic Banks.

Republic Act No. 12066. (2024). Corporate Recovery and Tax Incentives for Enterprises to Maximize Opportunities for Reinvigorating the Economy (CREATE MORE) Act.

Reuters. (2026, September 15). Coalition likely in Philippines' Muslim south with no clear winner in election.

Senge, P. (1990). The fifth discipline: The art and practice of the learning organization. Doubleday.

Silva, A. M. (2026). Reimagining BARMM's economic sectors: Building an integrated investment roadmap. AS Strategic Insights. https://asilvainnovations.github.io/barmm-investment-roadmap/ieb.html

Supreme Court of the Philippines. (2024, September 9). Province of Sulu v. Medialdea, G.R. No. 242255.

BIRD 2026–2035 · Chapter 7Page 21

Use the arrow keys or swipe to turn pages. Press C for contents.

Contents

In this document

Chapters

Prelims & Executive SummaryFront matter and executive summary Chapter 1Introduction, background, anchors and methodology Chapter 2Context, BEIE Framework and strategic diagnostics Chapter 3Strategic options, leverage points and the roadmap strategy Chapter 4Metrics, KPI benchmarking and calibration Chapter 5Balanced Scorecard, causal architecture and execution Chapter 6Implementation, action and annual investment plan Chapter 7Policy recommendations and the way forward Subject IndexNavigational index to all chapters